Self-build home: project plan
This is a free-to-use, open-access plan for the organisation, design and construction of self-build homes.
If you have ideas for things to add to the plan, you can either edit the plan and add them yourself, or submit a comment and we will add them for you.
There are a number of delivery routes for self-build homes:
- Purchase a kit house.
- Appoint a design and build contractor to design and build the home.
- Appoint consultants to design the home then get a contractor to build it.
- Appoint consultants to design the home then manage the construction yourself.
It may not be clear which route should be followed until initial assessments have been carried out, a plot located and a brief prepared. See: Develop a delivery strategy for more information.
It is also possible to work with other organisations such as social landlords, developers, or community groups to develop a self-build home, however, these projects are likely to follow a plan imposed by the lead organisation and so they are not covered here, although many of the project stages will be similar. Working with a developer is sometimes called ‘custom build’ rather than ‘self build’.
See Custom-build home for more information.
An outline project plan is presented below. It describes activities step-by-step from the first moment it becomes apparent a self-build home could be a possibility right through to occupation of the completed building. Most of the stages are common to all four self-build routes, but the appointment stages vary.
Clicking on any of the stages will take you to a detailed description of the tasks that need to be carried out.
Stage 1: Justify the project.
Stage 2: Prepare a brief.
Stage 3: Find a plot.
Stage 4: Develop a delivery strategy.
Stage 5: Raise finance.
Stage 6: Acquire the plot.
Stage 7: Appoint designers.
- Appoint consultants to design the home, or;
- Appoint a contractor to design the home, or;
- Appoint a supplier to design a kit house.
Stage 8: Prepare a concept design.
Stage 9: Submit a planning application.
Stage 10: Prepare a detailed design.
Stage 11: Submit a building regulations application.
Stage 12: Prepare production information.
Stage 13: Appoint contractors.
- Appoint a contractor to construct the home, or;
- Appoint a range of contractors and suppliers to construct the home, or;
- Confirm appointment of the design and build contractor to construct the home, or;
- Confirm appointment of the supplier to fabricate and install the kit house.
Stage 14: Prepare for construction.
Stage 16: Construction.
Stage 17: Occupy the home and rectify any defects.
Featured articles and news
Licensing construction in the UK
As the latest report and proposal to licence builders reaches Parliament.
Building Safety Alliance golden thread guidance
Extensive excel checklist of information with guidance document freely accessible.
Fair Payment Code and other payment initiatives
For fair and late payments, need to work together to add value.
Pre-planning delivery programmes and delay penalties
Proposed for housebuilders in government reform: Speeding Up Build Out.
High street health: converting a building for healthcare uses
The benefits of health centres acting as new anchor sites in the high street.
The Remarkable Pinwill Sisters: from ‘lady woodcarvers’ to professionals. Book review.
Skills gap and investment returns on apprenticeships
ECA welcomes new reports from JTL Training and The Electrotechnical Skills Partnership.
Committee report criticises UK retrofit schemes
CIOB responds to UK’s Energy Security and Net Zero Committee report.
Design and construction industry podcasts
Professional development, practice, the pandemic, platforms and podcasts. Have we missed anything?
C20 Society; Buildings at Risk List 2025
10 more buildings published with updates on the past decade of buildings featured.
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation, closing 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
From project managers to rising stars, sustainability pioneers and more.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
Comments
It seems that the handover information such as building manual, H&S files, and other operation and maintenance documents are not mentioned here.
Not surpised that most building owners do not know what is in their building.