Garnett Station Rehabilitation

Current Status

Construction began in September 2025. 

Updated Garnett Skip Stop Banner

RIDER ALERT: GARNETT SIX-WEEK SKIP STOP

From Saturday, Sept. 13 through Sunday, Oct. 26, 2025, Red and Gold Line trains will NOT stop at Garnett Station while we renovate the platform. Customers cannot exit or board a train at Garnett during this time. 

SERVICE IMPACTS FROM SATURDAY, SEPT. 13 – SUNDAY, OCT. 26, 2025:

  • Rail: Red and Gold Lines run as scheduled but won't stop at Garnett.  

  • Shuttle Service: A shuttle is available between Garnett and Five Points. Please allow an extra 15 minutes for your trip.
    • At Garnett, the shuttle boards on Brotherton Street (south end of station, next to the Greyhound Station).
    • At Five Points, the shuttle boards on Forsyth Street (west side of station). 

  • Station Access: There is no customer access to the station, including the concourse and plaza levels. 

  • Local Bus Service: No local MARTA buses currently serve Garnett Station. Route 40 on Peachtree Street operates as normal.

  Garnett Platform Tile Installation

Image Description: Crews are shown installing the new platform pavers on the south side of Garnett Station.

Project Overview

MARTA is renovating Garnett Station as part of its State of Good Repair Program. Garnett Station opened in 1981, and, after more than 40 years of wear and tear, existing pavers are in immediate need of repair to ensure a safe, accessible, and positive experience for customers. New pavers are also easier to clean, replace, and maintain long-term.

The total budget for Garnett Station Rehabilitation is $9.9 million. The six-week Skip Stop will save about 14 months of construction time and $5 million.

Bobcat moving debris at Garnett

Image Description: A crew member drives a compact tractor to move old platform pavers and other debris out of the way.

We Value Your Feedback 

We appreciate your patience and welcome your feedback on the project during construction. Click the link below to take an online survey: 

Garnett Station Rehab Survey – English

Garnett Station Rehab Survey - Español 

Key Project Features:

  • Demolition and replacement of existing platform pavers including cracked and missing pavers  
  • Staircase repair 
  • Replacement of worn windscreens to improve the appearance and natural lighting on the platform 
  • Heavy cleaning, pressure-washing, sealing and graffiti-resistant coating applied to concrete areas     

Future project works includes the replacement of the pavers on the concourse and plaza levels. Stay tuned for more updates here.

Garnett Tiles Before and After Image Description: The image above shows old and new platform pavers side-by-side. Old, damaged blue pavers are on the left. New, modern pavers that are smoother and easier to clean are on the right. 

Resources/Documents

Click below for sample communication and other partner resources for the Skip Stop. 

Access Partner Toolkit

Stay Informed

Stay tuned for more updates on this page and sign up for email updates below. 

Sign Up for Updates

For questions about MARTA service during this project, please contact Customer Service at 404-848-5000 or [email protected].  

For questions about this Station Rehabilitation project, please contact MARTA Project Manager: 

Tara King 
[email protected] 
404-848-5066  