The Wayback Machine - https://web.archive.org/web/20130127044526/http://www.world-nuclear.org:80/info/inf115_taiwan.html
 

Nuclear Power in Taiwan

(updated January 2012) 

  • Taiwan has six nuclear power reactors operating, and two advanced reactors are under construction. 
  • Nuclear power is considerably cheaper than alternatives. 

Taiwan imports 99% of its energy, which is vital to the rapidly industrialising economy.

Electricity demand was growing at almost 5% per year, but this is slowing to about 3.3% pa to 2013.  Nuclear power has been a significant part of the electricity supply for two decades and now provides one quarter of base-load power and 17% overall, though nuclear comprises only 11% of 46 GWe installed capacity.  Coal-fired plants comprise 26% of capacity and in 2008 delivered 38% of the power.  LNG provides 20% of the power.  Total power generated in 2008 was 238 billion kWh, nuclear being 17% of this, 40.8 billion kWh gross, 39.3 TWh net. 

The three nuclear plants comprise four General Electric boiling water reactors and two Westinghouse pressurised water reactors.  Construction of the first unit began in 1972.  They are all operated by the utility Taipower, under the Ministry of Economic Affairs and were expected to have 40-year lifetimes.  Five of the six units had undergone minor uprates by the end of 2008, resulting in net 44 MWe increase.

Operating Taiwan nuclear power reactors 

Units type MWe gross
 
MWe net Start up* Licenced to
Chinshan 1 BWR 636 604 1978 2018
Chinshan 2 BWR 636 604 1979 2019
Kuosheng 1 BWR 985 948 1981 2021
 
 Kuosheng 2 BWR 985 948 1983 2023
Maanshan 1 PWR 951 900 1984 2024
 
 Maanshan 2 PWR 951 923 1985 2025
Total (6) 4927 MWe net
 
   
* dates are for start of commercial operation.

 

In 2007 the Atomic Energy Council (AEC) said that Chinshan BWR plant had undergone a safety evaluation and was safe to run for a further 20 years following planned licence expiry in 2017. The AEC had approved this life extension, though in November 2011 a new national energy policy disallowed it and affirmed simply a 40-year operating life. Taipower had expected to seek 20-year licence renewals for all six reactors.

In 2009 Taipower said that it planned to replace the steam generators of the two Maanshan PWR reactors by about 2020 if it could obtain life extensions from the AEC.  This and other work is expected to yield uprates of some 440 MWe across the six reactors.

There are two 1350 MWe Advanced Boiling Water Reactors under construction at Lungmen, near Taipei. Initial plans to procure the units on an Engineering, Procurement and Construction (EPC) basis failed, and contacts were awarded to GE for the nuclear reactors, Mitsubishi for the turbines and others for the rest, making it a particularly difficult project to manage. Construction began in 1999 with intention of 2004 completion.

When the two reactors were one third complete a new cabinet cancelled the project but work resumed the following year later after legal appeal and a government resolution in favour.  The project was thus significantly delayed by this, in addition to other delays.  A date for completion of the first unit will be announced early in 2012 - in June 2011 it was undergoing pre-operational testing, with the second unit about a year behind.  Commercial operation was expected in 2012, but in November 2011 Taipower said 2014 at best.  Cost escalation due to the construction hiatus plus project management and engineering problems had pushed the projected cost to over US$ 2900/kW, and as of March 2009, $1.15 billion was required to finish the project, which was then 88.6% complete.   In 2011 the AEC was scathing concerning Taipower's management of the project.

 Taiwan nuclear reactors under construction 
 
  type MWe net  start-up commercial operation
Lungmen 1 ABWR 1300 2012? 2014-15
Lungmen 2
 
ABWR 1300 2012? 2015
 total (2)   2600    

also known as Taipei County plant, each unit 1350 MWe gross

In May 2009 Taipower was examining the prospects for six more reactors, starting with a pair at an established site to be on line about 2020, though more recently it has projected one further unit beyond Lungmen 1&2 being on line by 2025.

Following the Fukushima accident in March 2011, the AEC initiated a comprehensive nuclear safety review, and the first phase of this was completed in September. The AEC also strengthened its radiation protection capacity and contingency mechanisms, since Taiwan is very prone to seismic activity.  In January 2012 the AEC said that its post-Fukushima inspections found "no safety concerns" with the six operating nuclear units. It also required Taipower itself to review the nuclear plants' safety margins by following the European Union's reactor stress test requirements, with its report on this due by the end of February 2012.

Nuclear output on Taiwan is very cost competitive at US$ 1.9 cents/kWh in 2008 now that the six reactors have been depreciated.  Average Taiwan generation cost was 7.0 c/kWh in 2008, with coal-fired generation US$ 5.8 cents/kWh, and LNG US$ 11.25 cents/kWh.  During their first ten years of operation the Lungmen reactors are expected to generate at US$ 3.8 cents/kWh.

Fuel cycle & wastes

All materials and services are imported, including 850,000 SWU of enrichment.

A low-level radioactive waste storage facility is operated on Lan-Yu island by Taipower.

Policy for used fuel is direct disposal, though reprocessing is under consideration. Dry storage for Chinshan and Kuosheng will be needed. A geological repository is planned for 2032 operation.

Research & Development

There are four research reactors in operation on Taiwan, ranging up to 2.8 MW. TRR, a 40 MW heavy water reactor, was shut down in 1987 and was to be redesigned as a light water reactor. Two small research reactors are shut down and decommissioning.

Organisation

The Atomic Energy Council (AEC) consists of representatives from relevant government ministries. The Radwaste Administration is a subsidiary body and is regulator in respect to radioactive wastes. 

The Nuclear Regulatory Division is also part of the AEC, as is the Radiation Protection Division. The AEC is also responsible for safeguards.

The Atomic Energy Law came in to force in 1968 and various regulations have been promulgated under it.

In 2011 Taiwan and mainland China signed an agreement on nuclear safety and emergency reporting. Under the agreement, China and Taiwan will provide each other with information on their nuclear power plants, regulations and standards for nuclear safety, and exchange their experiences in nuclear safety and plant ageing. It also calls for them to cooperate on nuclear incident communications rated at INES Level 2 or above, environmental radiation monitoring, as well as emergency preparedness and response. Taiwan's AEC says that the agreement will promote cross-Strait nuclear power safety information transparency and enhance the safety and operating performance of nuclear power plants so as to ensure the safety of people on both sides.

Non-proliferation

All nuclear facilities on Taiwan are subject to a non-governmental safeguards agreement with the International Atomic Energy Agency, and all fall under full safeguards.

Taiwan signed the Nuclear Non-Proliferation Treaty (NPT) in 1968 and ratified it but after 1971 the People's Republic of China replaced Taiwan in the NPT and the IAEA. In terms of such treaties and organisations, and for those countries which adhere to a one-China Policy, Taiwan does not exist as an independent state. The USA recognises Taiwan as an independent state and has state to state relations with it. Taiwan has a unique status. Nuclear safeguards are applied in Taiwan under a trilateral agreement between Taiwan, the USA and the IAEA.

Thus the IAEA applies safeguards in Taiwan to all nuclear material and nuclear facilities as if it were an NPT non-nuclear-weapon state Party; it conducts regular inspections including Additional Protocol verification activities.

Main Sources:
 

Country Nuclear Power Profiles, IAEA, 2003.

 

 Facebook | Twitter | YouTube | Google+ | WNA Update  | Jobs |  Nuclear Portal |  Glossary  |  eShop  |  Picture Library 

© World Nuclear Association. All Rights Reserved
World Nuclear Association, registered in England and Wales, number 01215741. Registered office: 22a St James's Square London SW1Y 4JH UK
Â